THE MINISTRY OF PU\NNING AND INVESTMENT | SOCIALIST REPUBLIC OF VIET NAM |
No. 13/2010/TT-BKH | Hanoi, June 02, 2010 |
PROVIDING FORMS OF INVESTMENT MONITORING AND EVALUATION REPORTS
Pursuant to Law No. 38/2009/QH12 Amending and Supplementing a Number of Articles of Laws Concerning Capital Construction Investment;
Pursuant to Investment Law No. 59/2005/QH11;
Pursuant to the Government's Decree No. 113/2009/ND-CP of December 15. 2009. on investment monitoring and evaluation;
Pursuant to the Government's Decree No. II6/2008/ND-CP of November 14. 2008, defining the functions, tasks, powers and organizational structure of the Ministry of Planning and Investment;
The Ministry of Planning and Investment provides forms of investment monitoring and evaluation reports as follows:
Article 1. Scope of regulation and subjects of application
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2. This Circular applies to organizations and individuals involved in the elaboration of investment monitoring and evaluation reports.
Article 2. Forms of investment monitoring and evaluation reports
1. Forms of investment monitoring and evaluation reports issued together with this Circular include:
a/ Form No. 1: biannual and annual report on investment monitoring and evaluation;
b/ Form No. 2: monthly report on the implementation of investment projects with 30% or more state capital:
c/ Form No. 3: quarterly, biannual and annual report on monitoring and evaluating the implementation of investment projects with 30% or more state capital:
d/ Form No. 4: monitoring and evaluation report upon adjustment of investment projects with 30% or more state capital;
e/ Form No. 5: monitoring and evaluation report upon termination of investment projects with 30% or more state capital:
f/ Form No. 6: biannual and annual report on monitoring and evaluating the implementation of investment projects funded with other sources of capital.
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Article 3. Organization of implementation
1. This Circular takes effect on July 17. 2010.
2. Ministries, ministerial-level agencies, government-attached agencies, other central agencies. People's Committees at all levels and concerned organizations and individuals should
report problems arising in the course of implementation to the Ministry of Planning and Investment for timely consideration and settlement.-
MINISTER OF PLANNING AND INVESTMENT
Vo Hong Phuc
REPORT ON MONITORING AND ASSESSMENT OF ANNUAL AND BIANNUAL OVERALL INVESTMENT
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
---------------
No.: /BCGSDT
………, date… month.. year …….
REPORT ON MONITORING AND ASSESSMENT OF OVERAL INVESTMENT
(Biannual/annual)
To: ………………………………………………….
I. STATUS OF ISSUANCE OF DOCUMENTS GUIDING POLICIES AND LAW IN RELATION TO INVESTMENT UNDER AUTHORITY
- Specifying the guiding documents in the reporting period (Document number, issuance date and document abstract).
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
II. STATUS OF PLANNING MANAGEMENT(stating the situation and result of performance, the pluses and minuses, the causes and responsibilities of agencies and organizations concerned, the problems related to mechanism and policies and proposing the remedies).
1. Status of formulation, appraisal and approval of planning under the area of management.
2. The management of implementation of provisions as prescribed.
3. The main obstacles and proposal for remedies.
III. STATUS OF MANAGEMENT OF INVESTMENT PROJECTS WITH THE USE OF 30% OF STATE CAPITAL OR MORE (stating the situation and result of performance, the pluses and minuses, the causes and responsibilities of agencies and organizations concerned, the problems related to mechanism and policies and proposing the remedies).
1. Formulation, appraisal and approval of projects.
2. Status of project implementation
- Value of volume invested in the period; achievements against the plans;
- Status of disbursement of projects; achievements against the plans;
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- A number of projects adjusted in the period; the main reasons and remedies;
- Total project violated regulations on quality management; seriousness of the violation; major causes and remedies;
- A number of projects lost and wasted; degree of loss and waste, causes and treatment status of detected violations;
- A number of projects violating investment procedures; seriousness, causes and remedies.
3. Situation of implementing investment plans funded by the State:
- Plans for allocation of capital in the period;
- Results of disbursement of investment capital in the period;
- Situation of outstanding debt of investment capital (if any);
- Situation of waste and loss of investment capital (if any).
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
IV. STATUS OF MANAGEMENT OF INVESTMENT PROJECTS USING OTHER FUNDS (stating the situation and result of performance, the pluses and minuses, the causes and responsibilities of agencies and organizations concerned, the problems related to mechanism and policies and proposing the remedies).
1. Verifying and issuing certificate of investment
- Situation of project appraisal;
- A number of projects issued with certificate of investment in the period, total of registered investment capital (by economic sectors).
2. Managing the implementation of investment projects
- Investment capital plan as registered;
- Disbursement actually achieved.
3. Main obstacles and proposed remedies.
V. IMPLEMENTING THE INVESTMENT MONITORING AND ASSESSMENT (stating the situation and result of performance, the pluses and minuses, the causes and responsibilities of agencies and organizations concerned, the problems related to mechanism and policies and proposing the remedies).
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2. Assessment of quality of reports.
3. Result of examination and assessment of investment projects in the period
- A number of projects examined; achievements against the plan (attached to the list of projects decided on investment by the competent person and examined by the state management agency on investment);
- A number of projects assessed, achievements against the plan (attached to the list of assessed projects);
- The main findings after examining and evaluating the project.
4. Plan for examination and assessment of investment projects in the next period (attached to the list of projects expected to be examined and assessed in the period).
5. General assessment of investment monitoring and assessment in the period.
6. Main obstacles and proposed remedies.
VI. PROPOSALS AND RECOMMENDATIONS
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2. Proposals for implementation
(Attached to sub-forms: 01, 02, 03)
HEAD OF AGENCY
(Signature, seal)
STATUS OF INVESTMENT IN REPORTING PERIOD
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Total
Quarter I
Quarter II
Quarter III
Quarter IV
I. Projects using 30% of state capital or more
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Plan
Implementation
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
% completed
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Plan
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Implementation
% completed
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
III. Total
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Plan
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Implementation
% completed
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
% compared with the same period of last year
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Plan
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Implementation
% completed
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
% Compared with the same period of last year
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Plan
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Implementation
% completed
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
% Compared with the same period of last year
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
STATUS OF INVESTMENT MONITORING AND ASSESSMENT OF PROJECTS USING 30% STATE CAPITAL OR MORE
No.
Content
Total
Classification by group
A
B
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
I
Investment preparation
1
A number of projects planned for investment preparation in the period
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2
A number of projects appraised in the period
3
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
II
Investment implementation
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1
A number of investment projects implemented in the period
2
A number of new projects commenced during the period
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3
A number of projects whose reports on monitoring and assessment are made as prescribed in the period.
4
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
5
A number of projects whose project assessment is done in the period
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
6
A number of projects in breach of investment procedures detected in the period.
a
Not in accordance with the planning
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
b
Aprroval beyond power
c
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
7
A number of projects in breach of quality management detected in the period (under the current regulations of quality management)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
8
A number of projects wasted or lost detected in the period (after inspection, examination, audit and finalization)
a
Total investment capital of projects with waste and loss detected.
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
b
Total amount of loss and waste defined
9
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
a
A number of projects of slow progress due to investment procedures.
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
b
A number of projects of slow progress due to site clearance
c
A number of projects of slow progress due to capacity of investor, project management unit and contractors
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
d
A number of projects of slow progress due to timeless capital allocation
đ
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
10
A number of projects must be adjusted in the period
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
a
A number of projects whose objectives and investment scale must be adjusted
b
A number of projects whose investment capital must be adjusted
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
c
A number of projects whose investment progress must be adjusted
d
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
11
A number of projects whose performance must be stopped because of various reasons
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
12
A number of projects in need of selection of contractors in the period
a
Total package held for selection of contractor in the period
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
-
Contractor appointment
-
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
-
Open bidding
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
-
Hình thức khác Other forms
b
Total package in breach of bidding procedures detected in the period
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
-
Bidding performed not in accordance with regulation
-
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
III
End of investment, handover and putting of project into use
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1
A number of projects whose investment is ended in the period
2
A number of projects whose finalization procedures are done for project completion in the period
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3
A number of projects put into use but not effective (if any)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
STATUS OF INVESTMENT MONITORING FOR PROJECT USING OTHER FUNDS
No.
Target
Total
Classification by group
(1)
(2)
(3)
1
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
a
Total capital registered for investment
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
b
A number of projects whose verification procedures are done for issuance of Certificate of investment
c
A number of projects whose procedures for investment registration has been done
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2
A number of projects have been issued with Certificate of investment in the period
a
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
b
Adjustment of scale of investment capital
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
c
Adjustment of progress
d
Transfer of investor
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3
A number of projects inspected and assessed in the period
4
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
5
A number of projects in breach of regulations on environmental protection detected in the period
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
6
A number of projects in breach of regulations on land use detected in the period
7
A number of projects in breach of regulations on management of natural resources detected in the period
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
8
The projects whose Certificate of investment must be revoked
9
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
a
Owner’s contributed capital
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
b
Loans
c
Other legal mobilization
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
10
A number of projects terminated with their investment in the period
Notes: (1) Project under the approval of the Prime Minister for investment (2): Project with a total investment of 300 billion dong or more (except for projects specified at Point (1) ), (3): Project with a total investment of less than 300 billion dong.
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
NAME OF GOVERNING AGENCY
NAME OF INVESTOR
-------
SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
---------------
Số: / BCGSDGDT
………, date month year…….
REPORT ON MONITORING AND ASSESSMENT OF INVESTMENT
(Month …. year ….)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
To: ………………………………………………….
1. Status of project implementation
1.1. Project implementation progress
The volume of work done; accumulated work done from the beginning of the year and of the project; comparison with the plan.
1.2. Status of disbursement
- Value of volume of work done in a month; accumulated value of volume of work from the beginning of the year and of the project; comparison with the plan.
- Status of disbursement of investment capital in a month; accumulated disbursement value from the beginning of the year and of the project; comparison with the plan.
+ Construction and installation costs:
+ Equipment costs:
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2. Assessment of project implementation
2.1. Overall assessment of project implementation: (Overall assessment of the implementation of construction investment procedures, volume of implementation, disbursement progress,... assessment of the achievement compared with the plan, the existences and problems).
2.2. Analysis of existent causes
2.3. Solutions to handle the existences and obstacles.
3. Proposal
Proposing the supporting and handling measures of project’s problems (if any) to the person having competence in investment decision.
INVESTOR
(Signature and seal)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
NAME OF GOVERNING AGENCY
NAME OF INVESTOR
-------
SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
---------------
Số: /BCGSDGDT
………, date month year…….
REPORT ON MONITORING AND ASSESSMENT OF INVESTMENT IMPLEMENTATION
(Quarterly/Biannual/Yearly)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
To: ………………………………………………….
I. Content of report:
1. Status of project implementation:
1.1. Progress of project implementation: ( Preparation for technical design, site clearance and relocation, bidding and contract performance…)
1.2. Value of volume performed under the progress of contract implementation
1.3. Status of capital management and summary of disbursement result:
1.4. Quality of work achieved: (Describing the quality of work achieved in proportion to the values of work volume for each phase accepted and paid)
1.5. Other costs related to the project:
1.6. Changes related to the process of project implementation:
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2.1. Plan for implementation: (Stating the overall plan for each phase of project management in order to obtain the required progress);
2.2. Detailed plan of project implementation management contents: (Describing the detailed plan of each phase for work composition related to the phase of project management and implementation).
2.3. Results obtained compared with the proposed plan and adjustment of implementation plan to suit the requirements:
2.4. Quality assurance and effect of project management:
3. Status of information processing and feedback
3.1. Reporting information assurance: (The accuracy, truthfulness of reporting information)
3.2. Reporting information processing: (The timely reporting information processing after receipt of report for timely feedback to avoid adverse consequences to the project).
3.3. Result of arising problems: (Stating the results achieved through the process of settlement of arising problems during the project implementation).
II. Investor’s self-assessment and remark about the project:
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2. Project management:
3. Information processing and feedback:
III. Proposed implementation solution:
Proposing the supporting and handling measures of project’s problems (if any) to the person having competence in investment decision.
INVESTOR
(Signature and seal)
(Attached to subforms No.: 04, 05, 06, 07, 08, 09, 10)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Subform No.04 is reported only once in the first period;
- Subforms No. 04, 05, 06, 07, 08, 09, 10 are only reported in the periods of activity deployment related to the contents in these subforms;
- For projects which are decided on investment by Chairman of district and commune-level People’s Committee, in addition to sending reports to the person having competence in investment decision and the governing agency, other reports must be sent to the Service of Planning and Investment for summary.
1. Project name:
2. Project investor:
3. Project planning consultation organization:
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
4. Scale and capacity:
5. Project location:
6. Land use area:
7. Form of project management:
8. Project timeline:
- Approval date of investment decision:
- Project implementation time:
+ Starting time:
+ End time:
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
10. Investment capital:
11. Brief description of project:
….., date … month … year …..
INVESTOR
(Signature and seal)
PROGRESS OF TECHNICAL DESIGN FORMULATION
No.
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Name of contractor performing technical design
Approval date of technical design
Plan
Actuality
A number of documents
(1)
(2)
(3)
(4)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
(6)
1-
2-
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3-
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
….., date … month … year …..
INVESTOR
(Signature and seal)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
PROGRESS OF SITE CLEARANCE AND RELOCATION
No.
Name of sub-project / package / location
Date on which the competent authority approves the project to compensate for site clearance and relocation
Compensation date (site handover)
Plan
Actuality
Plan
Actuality
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
(2)
(3)
(4)
(5)
(6)
1-
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2-
3-
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
…
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
….., date … month … year …..
INVESTOR
(Signature and seal)
PROGRESS OF CAPITAL EXPENDITURE FOR IMPLEMENTATION OF SITE CLEARANCE AND RELOCATION PLAN
No.
Name of sub-project / package / location
Costs of site clearance and relocation
Management costs
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Accumulation
Plan
Spending
Plan
Spending
Plan
Spending
(1)
(2)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
(4)
(5)
(6)
(7)
(8)
(9)
1-
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2-
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3-
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
…
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
….., date … month … year …..
INVESTOR
(Signature and seal)
PROGRESS OF BIDDING IMPLEMENTATION
No.
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Package price
Form of biding
Method of bidding
Form of contract
Duration of the contract
Duration of bidding
Result of bidding
Plan
Actuality
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Bid-winning price
Increase (+), decrease (-) difference
Bid-winning contractor
(1)
(2)
(3)
(4)
(5)
(6)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
(8)
(9)
(10)
(11)
(12)
(13)
1-
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3-
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
…
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
….., date … month … year …..
INVESTOR
(Signature and seal)
PROGRESS OF CONTRACT PERFORMANCE
Unit: Million dong
No.
Package name
Number of contract
Contractor name
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Initial contract
Adjusted contract
Actual completion day
Value of work volume done (%)
Value paid
Contract value
Completion day
Contract value
Completion day
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Cumulation at the beginning of year
Cumulation after contract signing
Reporting time
Cumulation at the beginning of year
Cumulation after contract signing
(1)
(2)
(3)
(4)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
(6)
(7)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
(17)
1-
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2-
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3-
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
….., date … month … year …..
INVESTOR
(Signature and seal)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
SUMMARY OF PERFORMANCE AND PAYMENT OF PROJECT INVESTMENT CAPITAL
Unit: Million dong
No.
Content description
Investment capital plan
Value of work volume done at the site
Value of work volume accepted
Capital paid(advance+ work volume at site paid
Value of work volume accepted but unpaid
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Cumulation from commencement
In reporting period
Cumulation from commencement
In reporting period
Cumulation from commencement
In reporting period
Cumulation from commencement
Total
Advanced capital
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Advanced capital
(1)
(2)
(5)
(6)
(7)
(8)
(9)
(10)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
(12)
(13)
(14)
(15)
1-
Total
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2-
State capital
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3-
Other capital
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
-
Construction & installation
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
-
Equipment
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
-
Other costs
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
…..
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
….., date … month … year …..
INVESTOR
(Signature and seal)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
NAME OF GOVERNING AGENCY
NAME OF INVESTOR
-------
SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
---------------
Số: /BCGSDGDT
………, date month year…….
REPORT ON MONITORING AND ASSESSMENT OF INVESTMENT PROJECT
Project name: ……………………..
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
I. Information about project:
1. Project name:
2. Investor:
3. Project planning consultation organization:
5. Main objectives of project:
4. Scale and capacity:
5. Project location:
6. Land use area:
7. Form of project management:
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Approval date of investment decision:
- Project implementation time:
+ Starting time:
+ End time:
9. Total investment:
10. Investment capital:
11. Brief description of project:
II. Status of project implementation: (Reporting in detail the entire process of project implementation to the point of time applying for project adjustment
III. Content of project adjustment: (Stating main contents of project adjustment, components of adjusted project)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
(Comprehensively reviewing the project, stating the reasons and causes for project adjustment and responsibilities of the parties concerned in the process of formulation, appraisal, approval and implementation of the project as a basis of project adjustment and learning from experience for other projects ...)
V. Re-assessment of adjusted project:
VI. Proposal:
INVESTOR
(Signature and seal)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
---------------
Số: /BCGSDGDT
………, date month year…….
REPORT ON MONITORING AND ASSESSMENT OF PROJECT INVESTMENT TERMINATION
Project name: ……………………..
To: ………………………………………………….
I. Information about project:
1. Project name:
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3. Project planning consultation organization:
5. Main objectives of project:
4. Scale and capacity:
5. Project location:
6. Land use area:
7. Form of project management:
8. Project timeline:
- Approval date of investment decision
- Project implementation time:
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
+ End time:
9. Total investment:
10. Investment capital sources
11. Brief description of project:
12. Information about bidding result:
II. Content:
1. Summing up the whole process of project implementation:
Briefly describing the process of project impelementation from the preparation for implementation to the end of investment.
2. Summing up the achieved results of implementation of project:
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2.2. Result of financial implementation:
- Comparing the total investment by investment decision with the total actual disbursement value;
- Stating essential adjustment on total investment of project;
- Stating factors which effect the disbursement compared with the approved investment decision
2.3. Factors affecting the results of project implementation:
- Stating the factors which affect the results of project implementation including: Legal grounds, project management, bidding, procurement, site clearance and relocation engineering and technological issues...
- Advantages and difficulties and remedies that the investor has carried out.
2.4. Preliminarily stating social-economic efficiency compared with the project objectives:
The project implementation aims to the completion of project objectives and contribution to implementation of objectives and duties of the Government’s plan for social-economic development.
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
The project implementation effecting the relevant sectors and fields (Economy, science and technology, environment, culture and society, etc. ....).
2.6. The sustainability of project:
Stating the impacting factors and ensuring the sustainability and promoting the efficiency of the project.
2.3. Learning from experience from practicality of the project:
Lessons drawn from the project and recommendations (if any) in order to promote the efficiency, sustainability or overcome the limitations of the project.
INVESTOR
(Signature and seal)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
NAME OF GOVERNING AGENCY
NAME OF INVESTOR
-------
SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
---------------
Số: /BCGSDGDT
………, date month year…….
REPORT ON MONITORING AND ASSESSMENT OF INVESTMENT PROJECT IMPLEMENTATION
(Biannual/annual)
Project name: ……………………………….
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
I. Information about project:
1. Investor:
2. Main objectives of project:
3. Scale and capacity:
4. Project location:
5. Total investment and funds
6. Main timeline:
- Isue date of Certificate of investment;
- Date of commencement;
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
II. Status of project implementation
1. Progress of project implementation: (stating the results of main work implementation of the project; expected work volume done in the period, accumulation from the beginning of year and project and comparison with the plan).
2. Status of capital mobilization for the project: (specifying the result of capital mobilization for project implementation in the period based on the funds (investor’s capital, bank loans and legal mobilization); accumulation from the beginning of the year and project; comparison with the plan).
3. Status of disbursement (stating the disbursement of investment capital in the period; accumulated disbursement value from the beginning of the year and of the project; comparison with the plan.
4. Implementation of the requirements for environmental protection, land use, mineral and natural resources use: (stating the project work done to ensure the requirements of environmental regulations, the use of land, mineral and natural resources ...)
5. The implementation of contents of Certificate of investment: (stating contents done in accordance with provisions of Certificate of investment issued by each phase of project).
II. Proposals for solutions:
Proposing the supporting and handling measures of project’s problems (if any) to the competent agencies.
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
INVESTOR
(Signature and seal)
- 1 Decree No. 113/2009/ND-CP of December 15, 2009, on investment monitoring and evaluation
- 2 Law No. 38/2009/QH12 of June 19, 2009, amending and supplementing a number of articles of the Laws concerning capital construction investment
- 3 Decree No. 116/2008/ND-CP of November 14, 2008, defining the functions, tasks, powers and organizational structure of the Ministry of Planning and Investment.
- 4 Law no. 59/2005/QH11 of November 29, 2005 on investment