THE PRIME MINISTER | SOCIALIST REPUBLIC OF VIETNAM |
No.: 412/QD-TTg | Hanoi, April 11, 2007 |
DECISION
ON APPROVING THE INVESTMENT LIST OF A NUMBER OF IMPORTANT AND ESSENTIAL TRANSPORT INFRASTRUTURE PROJECTS IN PERIOD TILL 2020
THE PRIME MINISTER
Pursuant to the Law on Governmental Organization of December 25, 2001;
Pursuant to the Prime Minister’s Decision No. 290/2006/QD-TTg of December 29, 2006 approving the Scheme on “Orientations for attraction and use of official development assistance in the 2006 – 2010 period”;
At the proposal of the Ministry of Planning and Investment (Dispatch No. 1350 BKH/KCHT&DT of March 05, 2007 and No. 1811 BKH/KCHT&DT of March 20, 2007), the Ministry of Transport (Dispatch No. 1444/BGTVT-KHDT of March 21, 2007), the Ministry of Construction (Dispatch No. 546/BXD-XL of March 23, 2007), the State Bank of Vietnam (Dispatch No. 2360/NHNN-TD of March 21, 2007), the Ministry of Finance (Dispatch No. 4356/BTC-DT of March 29, 2007),
DECIDES:
Article 1. To approve the investment list of a number of important and essential transport infrastruture projects in period till 2020 with the following contents:
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- To mobilize resources to completely build one step of transport infrastructures in period till 2020, in which concentrating on investing in construction of important, essential projects, aim to contribute to boosting the implementation of industrialization – modernization of the country.
- In parallel with investing in important and essential transport infrastruture projects, it is necessary to maintain, upgrade in order to make the most of current transport infrastructure capacity and step by step complete the transport infrastructure system of the country in period till 2020
- As a basis for mobilizing, attracting investment capital sources (ODA capital, foreign direct investment capital, domestic capital sources and other capital sources) for investments in transport infrastructures.
- As a basis for supplementing, amending transport development plannings.
2. Specific targets:
- Period till to 2010:
+ Road traffic: to build a number of new road sections belong to the North – South expressway (Hanoi, HoChiMinh city – Can Tho), a number of expressways belong to 2 Corridors and 1 economic belt of Vietnam – China and at key economic regions; to open to the HoChiMinh route traffic according to the National Assembly’s Resolution; to upgrade, expand a number of road sections on the National highway 1 in order to enhance traffic opening capacity and reduce traffic congestion.
+ Railways: to step by step enhance the capacity, modernize the current North – South railroad, improve, and upgrade the Yen Vien – Lao Cai railroad; to boost the preparation work for commencement the North – South express railroad and railroads serving expoitation and production of aluminum, alumin in the provinces of Tay Nguyen area.
+ Seaways: to build international container transshipment port in Van Phong, Khanh Hoa province (start-up phase) and the Northen gateway area in Lach Huyen, Hai Phong city; to build fairways for large-tonnage seagoing vessels to Hau river.
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- The 2010 – 2020 period.
+ Road traffic: to continue building priority stations on the North – South expressway, complete building expressway belong to 2 Corridors and 1 economic belt of Vietnam – China; to build the expressway from Dau Giay, Dong Nai province to Da Lat, Lam Dong province, continue to upgrade, expand a number of sections belong to the National highway 1 so as to remain it is being the arterial traffic axis of the country in period till to 2020
+ Railways: to carry out building the Hanoi – Ho Chi Minh City express railway, Lao Cai – Hanoi – Hai Phong railway; to improve, upgrade the Dong Dang – Hanoi railway to symmetrical railroads; to complete building the railroads serving the expoitation and production of alumin – aluminum in provinces of Tay Nguyen area.
+ Seaways: to continue investing in enhancing the capacity of the international container transshipment port in Van Phong, Khanh Hoa province and the Northen gateway port in Lach Huyen, Hai Phong City in accordance with the plannings.
+ Airways: to build the international airport in Long Thanh, Dong Nai province.
3. Development investment capital demand:
Total development investment capital demand for projects on the estimated list is approximately 67,570 million USD, in which the capital sources being identified is 4,418 million USD (including the projects which have had investment decision or signed the loan aggrement)
4. List of a number of important and essential transport infrastructure projects in period till to 2020 (the attached Annex)
Article 2. To organize the implementation:
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
a) To review, adjust plannings of transport development so as to ensure conforming to other relevant plannings. To prioritize completion plannings of development of expressway system and the express railway system in period till to 2020 and the vision after 2020; to carry out detailed plannings of the North – South expressway and the North – South express railway.
b) To continue guiding to boost the progress of the projects which have been granted the Investment decision.
c) Regarding projects expected using the domestic capital sources, to choose the priority projects and studying to suggest capital mobilization mechanisms for each of the projects; synchronously collaborate with concerned agencies to promote investment, towards prioritizing non-state budget sources from economic sectors
d) To concentrate on completing the Hanoi – Ho Chi Minh City express railroad project investment report as the basis for submitting to the National Assembly to approve the investment policies.
e) To biannually report to the Prime Minister and send to the Ministry of Planning and Investment, the Ministry of Finance about the implementation situation of the projects in the list.
2. The Ministry of Planning and Investment:
a) To assume the prime responsibility and coordinate with concerned agencies to review, update, add the projects in the list into the master plan for socio-economic development, region plannings till to 2010 and orientations towards the following years
b) To assume the prime responsibility and coordinate with concerned agencies to create plans on capital mobilizing and calling for projects expected using ODA capital, foreign direct investment so as to invest in projects in accordance with the progress requirement on the principle of ensuring macro-economic balancing of the development investment sources.
c) To assume the prime responsibility and coordinate with the Ministry of Finance in performing the function of inspecting, supervising the allocation and utilization of the development investment capital sources so as to ensuring the right purposes and investment efficiency.
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3. Concerned ministries and branches:
Within the scope of their functions, tasks and powers, bearing responsibility for collaborating with the Ministry of Transport, the Ministry of Planning and Investment to carry out the targets of this Decision.
4. Concerned People’s committee of centrally-affiliated cities and provinces:
a) To collaborate with the Ministry of Transport to review, adjust the plannings, plans for transport development in period till to 2010 and the orientation towards the following years;
b) To update, add the projects in the list into the plannings, plans for local socio-economic development in accordance with general plannings and plans;
c) To bear responsibility for conducting works of compensation, support, resettlement for land clearance as provided for, satisfying the requirements and the progress of project implementation.
Artivle 3: This Decision takes effect from the date of signing.
Article 4. Ministers, heads of concerned agencies, presidents of concerned People’s committee of centrally-affiliated cities and provinces shall bear responsibility for the implementation of this Decision./.
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
THE PRIME MINISTER
Nguyen Tan Dung
ANEX
LIST OF A NUMBER OF IMPORTANT AND ESSENTIAL TRANSPORT INFRASTRUTURE PROJECTS IN PERIOD TILL TO 2020
(Attached to the April 11, 2007 Decision No. 412/QĐ-TTg of the Prime Minister)
Unit: million USD
No.
Name of projects
Estimated scale of construction
Estimated deployment duration
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Divergence of investment
Expected capital source
Note
Till to 2010
2010-2020
1
2
3
4
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
6
7
8
9
AMOUNT
67,575
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
45,143
capital of the investment divergence in the 2010 period and 2010 – 2020 period of some unidentified projects
A
ROAD TRAFFIC
20,043
6,373
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
I
Expressway
16,927
3,257
4,895
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
North – South expressway projects, including:
12,986
2,404
817
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1
Cau Gie – Ninh Binh section (phase 1)
50 km
2005 - 2009
441
441
Enterprises and State budget
Investment Decision No. 323/QD-TTg of April 10, 2005
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Ninh Binh – Thanh Hoa section
60 km
Started in 2009
529
Japan’s ODA and co-donors
Having commitments between Vietnam’s Government and Japan’s Government
3
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Started in 2009
Japan’s ODA and co-donors
ditto
- Thanh Hoa – Vinh section
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1,217
- Vinh – Bai Vot (Ha Tinh) section
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Unidentified
4
Hue – Da Nang section
105 km
Stated in 2009
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Japan’s ODA or BOT
5
Da Nang – Quang Ngai section
125 km
Started in 2009
1,103
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Japan’s ODA and co-donors
Having commitments between Vietnam’s Government and Japan’s Government
6
Quang Ngai – Quy Nhon section
180 km
2011 – 2015
1,562
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Japan’s ODA and co-donors
ditto
7
Nha Trang – Dau Giay section
400 km
Started in 2009
3,528
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
ditto
8
Ho Chi Minh – Long Thanh – Dau Giay section
55km, 6-8 lanes
2008 – 2012
1,180
618
562
ODA + OCR+ Enterprises or BOT
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
9
Ho Chi Minh – Trung Luong section
45 km
2005 – 2008
600
600
Advance State budget, sale of the toll collection right
Investment Decision No. 1286/QĐ-TTg of December 06th 2004
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Trung Luong – My Thuan – Can Tho section
82 km; 4-6 lanes
Started in 2008
1,000
745
255
Japan’s ODA and co-donors or BOT
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3,841
853
2,988
1
Hanoi – Lao Cai route
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Phase 1
245 km, 2 – 4 lanes
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
653
653
ODA + OCR + State budget
- Phase 2
Remaining 19 km, expanding to 4 – 6 lanes
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2
Hanoi – Hai Phong route
100 km
Started in 2008
938
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
738
BOT
3
Bac Ninh – Lang Son route
140 km; 6 lanes
Started in 2010
1,400
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
China’s ODA or BOT
4
Ha Long – Mong Cai route
170 km; 4 – lanes
Started in 2010
850
850
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Expressway projects within key Economic Regions, including:
1,000
1,000
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1
Dau Giay – Da Lat route
230 km; 4 lanes
After 2010
1,000
1,000
Japan’s ODA and co-donors or BOT
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
HoChiMinh Highway
2,564
2,564
1
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3167 km
2000-2010
2,564
2,564
Public bonds, other sources
Excluding large bridge projects
2
HoChiMinh Highway (2010 – 2020 period)
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2010-2020
Chưa xác định
Chưa xác định
Public bonds, other sources
III
Large bridges on HoChiMinh Highway:
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
552
552
1
Vam Cong bridge
2074 md cầu; 16.47 km of the bridge ends
Started in 2008
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
316
Asia Development Bank’s ODA
2
Cao Lanh bridge
2073 md; 6 km of the bridge ends
Started in 2008
236
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Asia Development Bank’s ODA
B
RAILWAYS
44,320
5,920
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1
Building the Hanoi – Ho Chi Minh city express railway
1630 km
Started in 2009
33,000
3,000
30,000
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Having commitments between Vietnam’s Government and Japan’s Government
Railway projects within 2 Corridors and 1 economic belt Vietnam – China, including::
11,320
2,920
8,400
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
1
Improving, upgrading Cai Yen Vien – Lao Cai railway
280 km
2007-2010
160
160
ODA (France + Asia Development Bank’s) + State budget
Having signed with Asia Development Bank, Agreement No. 2302 VIE(SF) of January 16, 2007
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Building Lao Cai – Hanoi – Hai Phong railway
398 km; 1,435m format
After 2020
9,760
2,760
7,000
China’s ODA
3
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
165 km
After 2010
100
100
China’s ODA
4
Building railways serving the exploitation, production of alumin – aluminum in provinces of Tay Nguyen area
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2010 - 2020
1,300
1,300
BOT or enterprises exploiting and producing alumin
C
SEAWAYS
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
584
434
150
1
Building international container transshipment port in Van Phong, Khanh Hoa province.
2 starting harbors
2007 – 2010
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
197
Enterprises
Assigned to Vietnam Maritime Corporation to chair the mobilization of investment capital
2
Building the Northen gateway port in Lach Huyen, Hai Phong city (including Dinh Vu bridge)
187
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
- Building a container depot
4 million ton/year
Started in 2008
90
90
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Enterprises
Assigned to Vietnam Maritime Corporation to chair the mobilization of investment capital
- Building Dinh Vu bridge
Started in 2008
97
97
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
3
Building fairways for large-tonnage seagoing vessels to enter Hau river.
Opening fairways for 10,000 DWT ships
2009 – 2012
200
50
150
State budget
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
D
AIRWAYS
2,628
840
1,788
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
Building Duong To – Phu Quoc international airport
2 million passengers/year
2008 – 2012
156
56
100
FDI
2
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
8 - 10 million passengers/year
2008 – 2011
388
300
88
Japan’s ODA
3
Building passenger terminal – Da Nang international airport
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2007-2010
84
84
State budget + enterprises
Decision No. 385/QD-TTg of April 20, 2004 and Official Dispatch No. 2063/TTg-CN of December 18, 2006
4
Long Thanh international airport
25 million passengers/year
...
...
...
Mọi chi tiết xin liên hệ: ĐT: (028) 3930 3279 DĐ: 0906 22 99 66
2,000
400
1,600
FDI